Working draftMar 26 2026

Memorandum

Phase Zero done right

To
The executive sponsor
From
David Apollon
Re
The assessment and business case that de-risk an ERP program before the first dollar of build is spent
Date
8 min read

Most ERP programs are won or lost before they officially start. Phase Zero is where you buy down the risk, if you do it honestly.

The short version. Before the integrator arrives, build five things: an honest assessment of where you stand today; written scope, with a standard-versus-customization posture you hold; an operating model with real decision rights and backfill for the people you put on the program; a cost estimate and business case you built yourself; and an executive coalition that actually agrees on what the program is for. All five are cheapest to settle now, while nothing is committed.

By the time most ERP programs hold their kickoff, the outcome is already half decided. The scope was set in a hurry, the timeline came off a vendor slide, and the business case promises numbers nobody can trace back to a real operating decision. The build hasn't started, but the program is already carrying risk it doesn't know about.

Phase Zero is the work you do before any of that gets locked in: an honest assessment of where you stand, a business case you can defend, and the mobilization that turns a budget line into a program. Done right, it's the cheapest risk reduction you'll ever buy.

Exhibit 1
Blueprint floor plan of the five Phase Zero rooms: current-state assessment, scope and guardrails, operating model, cost case and executive coalition, with the front door marked where the SI arrives
The five rooms to build before the integrator walks in the door. Open full size

1 The calls you make here shape everything downstream

Cost, timeline, scope and the fights you'll have in year two all trace back to decisions made in this window. If you skip them, you end up improvising under pressure with tens of millions already committed.

Phase Zero is

not a procurement checkbox

not the week you spend writing an RFP

not a formality you rush to reach the "real" work

deciding what problem you're solving and what good looks like, and testing whether the organization can absorb the change.

2 Start from where the program really is

Where the program really is and where the steering deck says it is are usually further apart than anyone wants to admit, and the program pays for every inch of that gap later. A real assessment looks hard at four things.

Exhibit 2What a real assessment looks for, and what it costs to skip
AssessWhat you're actually looking forWhat it costs to skip
ProcessHow work gets done today, including the workarounds and the spreadsheets nobody mentions in a design workshopDesigning for the documented process, then discovering the real one in testing
Data qualityWhether your master data can survive a migrationPouring bad data into an expensive new system and calling it transformation
Organizational readinessWhether the people who have to adopt this are equipped and willingChange management stays a line item nobody owns until go-live proves it
TechnologyThe environment, the integrations, the dependencies, and the legacy systems that were supposed to be gone 2 years agoAn integration count that doubles after the estimate was signed

3 Write the scope down, or it grows one request at a time

Decide what's in and what's out before the program starts, and write it down. Scope left vague expands one reasonable-sounding request at a time, until the timeline and the budget no longer mean anything. Set your posture on standard versus customization early, too, and hold it.

Every time you bend the software to match how you work today, you pay for it in build, in testing and in every upgrade for the life of the system.

4 Decide who decides before the first hard decision lands

Stand up the PMO and the governance you'll actually use, rather than a wiring diagram that looks impressive in a board pack and collapses the first time two executives disagree. That means clear decision rights, a real escalation path, and a cadence people respect.

Then be honest about resourcing. If you put your best people on the program, and you should, somebody has to do their day jobs. Backfill them, or the business suffers while the program runs.

5 Build your own estimate, and a business case you can measure

Build your cost and timeline independently. The vendor is selling, and its estimate reflects that. You need a number you can stand behind in front of the board, with real contingency in it, rather than a figure engineered to clear an approval gate.

Hold the business case to the same standard. Promise benefits you can measure, because at benefits-realization time someone will hold you to them. Tie every claim to a real outcome: a process that gets faster, a cost that comes out, a risk that goes away. The inflated ROI that wins approval today is the number that comes back to embarrass you in 2 years.

2yearsuntil the inflated ROI that won approval comes back to embarrass you

Exhibit 3Every call you skip in Phase Zero comes due after the SI arrives
Current-state assessmentdiscovered during testing
Scope and guardrailsexpands one request at a time
Operating modeltested by the first hard decision
Cost and business casethe ROI comes back in 2 years
Executive coalitionresurfaces mid-build at ten times the cost
Each row is one of the five rooms. The ring is the call you can make in Phase Zero. Skip it and the cost moves right, to the point where the program finds out. The spacing is illustrative.

6 A signed budget doesn't mean your sponsors agree

A signature on a budget tells you the money is available. It tells you nothing about whether your sponsors agree on what this program is for.

Surface the disagreements now, while they're still cheap to resolve: the function that quietly thinks the scope is wrong, the executive who never wanted this platform, the two leaders with incompatible pictures of the target state. Those tensions don't go away because nobody named them. They resurface mid-build, when changing course costs ten times as much. A program without a real coalition behind it is starved of decisions and attention until, one day, everyone agrees it was always going to be hard.

10×what changing course costs when the tensions nobody named resurface mid-build

The time and money you put into Phase Zero is the highest-return spend in the program. It's also the easiest to cut, because nothing has visibly gone wrong yet. Cut it and the cost comes back later, with interest.

D.A.

9Nation ConsultingMemorandum: Phase Zero done rightWorking draft

Let's talk

Put independent eyes on your program.

If you're betting tens of millions on an ERP program, a candid second opinion is the cheapest insurance you'll buy.