← All insights

Vendor & SI · Change control

The change order autopsy

Three change orders taken apart on the table: what triggered each one, what it cost, and the clause that would have stopped it. Then check your own SOW against the same eight tells.

A change order is rarely a surprise to the vendor, and that's the part buyers get wrong. Most of the change orders I've watched land on steering committee tables were foreseeable at signature, and some were structured at signature. The work was always going to be needed. The only question was whether it would be priced into the deal while you had leverage, or sold to you later when you had none.

The three cases below come from real programs. Two are from the field, anonymized and rounded. The third is from the public record of an ERP lawsuit.

Case 01

The appendix that was always going to bill you

Cost
~$90K
Source
From the field, anonymized and rounded
Change orderFixed-fee deployment
PhaseTest, months into the program

Foreseeable, essential work. The program was always going to reach testing and need this support.

DescriptionActivate the guided test services appendix

It sat in the original SOW the whole time, detailed and effectively priced.

Reason for changeDeliverables now in scope as originally outlined in that appendix

“As originally outlined” means the scope existed at signature.

Amount~$90,000

Billed as a change, for work everyone knew was coming.

Preventable at signature

Findings

The setup

A fixed-fee deployment. Testing support was written into the original SOW as a separate "guided test services" appendix: described in detail, effectively priced, and deliberately held out of base scope.

The trigger

Months in, the program hit the test phase and needed exactly that support. The appendix was activated through a change order.

The invoice

Roughly $90,000. The change-order reason field said the deliverables were "now in scope as originally outlined" in that appendix. Nothing improper occurred. The foreseeable, essential work of testing had been structured from day one to convert into a paid change later.

The clause that would have stopped it

Before signing, walk every appendix and assumption and ask whether it's foreseeable work structured to become a change order. Anything essential moves into base scope. Anything genuinely optional gets pre-priced with a fixed cap, so predictable work can't be sold to you twice.

Verdict: preventable at signature. The tell was visible in the structure of the document: detailed, priced-ready scope sitting outside the base fee.

Case 02

The last mile of data

Cost
T&M, open-ended
Source
From the field, anonymized and rounded
Change order"Data conversion" in the SOW
TimingMid-conversion, behind schedule

Their conversion consultants sat idle, still billing.

WorkRemediation support for legacy data that the client owned

The assumptions section put cleansing on the client.

BasisTime and materials

Priced when the client had nowhere else to go.

AmountT&M, open-ended
Followed byA schedule-delay change order

A second invoice from the same assumption.

The most predictable

Findings

The setup

The SOW gave the vendor "data conversion." Read closely, the vendor owned only the last mile: loading files the client delivered. Cleansing and remediation stayed with the client, buried in the assumptions section.

The trigger

In practice 10 to 20% of legacy data typically needs business remediation before it will load. The client team found this out mid-conversion, behind schedule, with the SI's conversion consultants idle and billing.

The invoice

Remediation support was sold back on time-and-materials at the moment of maximum desperation. A schedule-delay change order followed when integrated testing surfaced the data issues the client now owned.

The clause that would have stopped it

Define conversion ownership end to end: profiling, cleansing rules, mock conversions with exit criteria, load, reconciliation. If the vendor owns loading only, price the remediation support in base scope now, at rate-card prices, and strike any assumption that converts client-owned data work into schedule-delay change orders.

Verdict: the most common change order in ERP, and the most predictable. If your SOW says "client provides clean data," you've already bought this change order; the invoice just hasn't arrived.

Case 03

Fifty-one change orders

Cost
$23M
Source
From the public record of an ERP lawsuit
Change order log$69M implementation, fixed fee
ContractFixed fee, with a major integrator

Fixed fee is supposed to put execution risk on the vendor.

Change orders51

Each one billed work the narrow scope left out.

Total$23M
ProgramRoughly $94M
Go-liveSlipped five times over eighteen months

Damages claimed in the lawsuit: more than $172M.

Invoiced 51 times

Findings

The setup

From the public record. A manufacturer signed a $69M implementation with a major integrator. The deal was fixed fee, which on paper shifts execution risk to the vendor.

The trigger

Vendors claw fixed-fee risk back two ways: they define scope narrowly and bill everything outside it, or they pad the bid with contingency. Here the narrow scope definition did the work, one change order at a time.

The invoice

51 change orders totaling $23M, taking the program to roughly $94M. Go-live slipped five times over eighteen months. The customer ultimately claimed damages exceeding $172M in litigation.

Case 03 in four numbers

  1. Signed, fixed fee$69M
  2. 51 change orders$23M
  3. The program, roughly$94M
  4. Damages claimed, more than$172M
From the public record of the lawsuit. Go-live slipped five times over eighteen months.

The clause that would have stopped it

Define precisely what counts as a change order, price every change against a rate card negotiated before work begins, and make the SI absorb the cost of its own estimating errors and omissions. A count threshold helps too: past an agreed number of change orders, executive review triggers automatically on both sides.

Verdict: one contract structure, invoiced 51 times.

A contract open on a stainless steel examination table under a surgical lamp, one clause circled in red ink, red flags marking clauses, a scalpel and reading glasses beside it
The autopsy, performed where it should be: before signature, while the clauses can still be rewritten.

Check your own SOW: the 8 tells

You can check every one of these before signature, from the document alone. Tick what's true of the SOW in front of you.

Change order exposure checkBefore signature

What to do with one that's already on your desk

The sequence is short. First, test the change order against the original SOW yourself before anyone negotiates price. A surprising share of change orders describe work the base scope already covers, once you read the base scope as carefully as the vendor did. Then price it against the rate card, not against a fresh quote. Then ask the question that changes the conversation: was this foreseeable at signature, and if so, why is it a change?

On paper the change-control board handles all this. In practice the board approves what the program manager brings it, which is why the review has to happen before the request reaches the agenda.

Each invoice had a clause that would have stopped it

Every ambiguity in a signed SOW resolves in the vendor's favor. That's why change-order discipline comes down to drafting decisions you make before you sign, and why each of the three cases above maps to one.

CaseCostThe clause
01The appendix~$90KEssential work goes into base scope. Optional work is pre-priced with a fixed cap.
02The last mile of dataT&M, open-endedConversion ownership defined end to end, with remediation support priced in base scope.
03Fifty-one change orders$23MA precise definition of a change, a pre-negotiated rate card, and the SI absorbing its own estimating errors.

Where 9Nation fits

I review SOWs and live change orders for buyers: the appendix walk, the assumptions rewrite, and the rate-card structure, done before signature while you still have leverage. The full negotiation guide is free at Negotiating with your System Implementer, and the defense sheet below travels well into a steering committee.

Let's talk

Put independent eyes on your program.

If you're betting tens of millions on an ERP program, a candid second opinion is the cheapest insurance you'll buy.